This FAQ addresses common mechanic’s lien questions for construction projects in Rochester. Kushnick Pallaci PLLC assists with New York mechanic’s liens and related payment disputes.
1. Who may file a lien?
Eligibility depends on the work, contractual relationship, owner consent or request, project classification and other statutory requirements. Lien Law § 3 governs qualifying private-improvement claims; § 5 addresses public contract funds. Review licensing and the available lien fund. Not every unpaid construction-related charge is lienable.
2. How long do I have to file?
For private improvements, § 10 generally provides eight months from the last qualifying work or materials, or four months for a single-family dwelling. Certain developer-owned subdivision properties are excepted from the single-family definition. A lien for retainage has a separate 90-day rule measured from when retainage was due to be released.
A public-improvement lien may be filed before completion and acceptance and within 30 days after both events under § 12. Do not assume the date of your last invoice controls the public-lien period.
3. Where do I file, and what about service?
A private lien on property located in Monroe County is filed with that county’s clerk; confirm the actual property location and any additional county involved. Public liens use the specified public officials and fund custodian instead. Filing alone is insufficient: private owner and contracting-party service and the 35-day proof-of-service requirement must be addressed under § 11 and § 11-b. Public liens follow § 11-c.
4. How long does a filed lien last?
Generally one year, unless properly continued. Act before expiration. Under § 17, a first private-lien extension for a project other than a single-family dwelling may generally be filed; later extensions require a court order. A single-family lien requires a court order for an extension. Timely foreclosure and the required notice of pendency may also continue a lien, with different rules where a bond or deposit has discharged it from the property. Public liens follow § 18. A demand to enforce can require earlier action.
5. How is a lien enforced?
Enforcement requires a lawsuit, appropriate parties, proof of the claim and compliance with applicable procedural requirements. Private-property foreclosure, public-fund enforcement and claims against substituted security differ. Filing does not guarantee payment. See the firm’s lien foreclosure and defense practice.
6. What if I receive a lien?
Review validity, amount, service, deadlines and the underlying dispute. Possible responses include negotiated payment or settlement, itemization, a court challenge, a demand to enforce, or a bond or deposit where appropriate. Bonding changes the security; it does not necessarily end the claim. Ignoring the lien can affect title, financing or litigation rights.
7. What if the lien is inaccurate?
Some errors may permit amendment or substantial-compliance analysis; others can defeat the lien. Willful exaggeration can void the entire lien under § 39. In a qualifying enforcement proceeding, § 39-a addresses the exaggeration amount, discharge bond premium or deposit interest and reasonable fees for securing discharge. It does not impose automatic triple damages.
Contact managing member Vincent T. Pallaci at 631-752-7100 or vtp@kushnicklaw.com. See the firm’s current Long Island and New York City office information.
Attorney Advertising. General information, not legal advice or a calculation of any particular deadline.
No comments:
Post a Comment